NWAnews.com :: Northwest Arkansas Northwest Arkansas Times

Fayetteville capital improvements

Posted on Monday, July 7, 2008

URL: http://www.nwanews.com/nwat/News/66859/

Water sewer improvement projects 1. Hamestring sewer lift station Construct a 36 million gallon per day (mgd ) capacity sewer pump station; $ 6, 909, 800 cost Construction substantially complete; estimated completion in May 2008 Brasfield & Gorrie Contractors 2. 48 ” gravity sewer line — Gregg to Hamestring Construct 24, 751 ’ of 48 ” gravity sewer pipe line and 3, 876 ’ of 30 ” sewer pressure pipe line; $ 10, 970, 164 cost Construction substantially complete Oscar Renda Contractors 3. Force mains — Hamestring to West Plant Construct 21, 740 ’ of 24 and 30 ” sewer force pipe lines; $ 4, 752, 287 cost Construction complete Garney Construction 4. Broyles Road water line Construct 3, 100 ’ of 12 ” water line; cost included with West Side Water Treatment Plant — No. 5 Construction complete Brasfield & Gorrie Contractors Broyles Road Construct 5, 900 ’ of two-lane asphalt road; $ 3, 737, 966 Construction 74. 17 percent complete Estimated completion June 2008 Dean Crowder Construction 5. West Side Waste Water Treatment Plant Construct a new 10 mgd (average daily flow ) wastewater treatment plant $ 60, 398, 785 cost Construction substantially complete Brasfield & Gorrie Contractors 6. Wetlands mitigation Construct and plant 25. 5 acres of wetlands Construction under way in multiple small contracts 7. Owl Creek lift station force main Upgrade the existing sewer pump station and install 11, 600 ’ of (estimated 15 ” sewer pressure pipe line Scope of work under review 8. Porter Road to Hamestring sewer line Construct 14, 100 ’ of 21-24 ” gravity sewer pipe line; $ 7, 186, 957 cost Construction substantially complete Oscar Renda Contractors

9. North Street to Poplar to Van Asche Road sewer line

Construct 13, 900 ’ of mostly 24-33 ” gravity sewer pipe line; $ 4, 433, 820 cost

Construction complete

T-G Excavating Contractor

10. Gregg Avenue sewer lift station

Construct a 19 mgd capacity sewer pump station; $ 1, 527, 000 cost

Construction substantially complete

Crossland Heavy Contractors Inc.

11. Old Wire Road to Gregg Avenue sewer line

Construct 15, 770 ’ of 21-36 ” gravity sewer pipe line; cost included with Porter to Hamestring — No. 8

Construction substantially complete

Oscar Renda Contractors

12. East Side Waste Water Treatment Plant renovation

Phase 1 (EP-2 )

Upgrade odor control, solids handling, headworks at the Noland wastewater treatment plant; $ 14, 836, 631 cost

Construction complete

Archer Western Contractors

Phase 1 (EP-4 )

Upgrade effluent aeration, $ 66, 460 cost

Construction complete

BlueinGreen Contractors

Phase 2 (EP-1 )

Increase wet weather capacity, remove the effluent pumping station; $ 1, 336, 886 cost

Construction substantially complete

Wilson Brothers Contractors

Phase 3 (EP-3 )

Remove effluent pumping station, upgrade aeration basin; $ 1, 646, 900, estimated cost — not yet bid.

Bid date June 19, 2008; estimated completion of August 2009

13. Mally Wagnon sewer lift station and force main

Replace sewer pump stations, install 4, 000 ’ of 16 ” sewer force pipe line; $ 1, 393, 880 cost

Construction substantially complete

Garney Construction

14. Happy Hollow to Noland Waste Water Treatment Plant sewer line

Construct 26, 458 ’ of 42 ” gravity sewer pipe line; $ 10, 431, 995 cost

Construction 81. 70 percent complete; estimated completion date of September 2008

Rosetta Construction

15. Razorback Road to Happy Hollow sewer line

Construct 13, 489 ’ of 21-30 ” gravity sewer pipe line; $ 6, 015, 000 estimated cost — not yet bid

Tentative bid date of August 2008; estimated completion of September 2009

16. South Mountain to Industrial Park sewer line

Construct 4, 084 ’ of 10 ” gravity sewer pipe line, $ 572, 000 estimated cost — not yet bid Tentative bid date of August 2008; estimated completion of September 2009 31. Lift station upgrade Upgrade sewer lift stations 13, 14 and 16; $ 460, 367 cost Construction 89 percent complete; estimated completion date of July 2008 OMI is executing work Other major capital

improvements 17. U. S. 62 west water line Relocating the water line along U. S. 62 due to widening from North Hunter to County Road 647; $ 1, 180, 177 cost Construction complete 18. Sanitary sewer rehab Construct 13, 067 ’ of 8-15 ” gravity sewer pipe line at various locations citywide; $ 2, 266, 606 cost Construction complete T-G Excavating Contractors 19. North College water line replacement — Maple to North Replacing old water lines along College Avenue from Maple Street to North Street; $ 1, 377, 141 cost Construction complete 20. 24 ” water line improvements Replacing water lines along Custer Lane and Morningside Drive; $ 908, 710 cost

• Construction complete

Crossland Heavy Contractors

21. Razorback Road water line relocation

Relocating water line along Razorback Road due to widening from 6 th Street to 15 th street; $ 722, 891 cost

Construction complete

22. Arkansas 16 water line relocation — Rupple Road to Double Springs Road

Relocating the water line along Arkansas 16 due to widen Rupple Road to Double Springs Road; $ 1, 591, 426 cost

Construction complete

23. Mount Sequoyah water and sewer

Construct approximately 6, 900 ’ of water line and 600 ’ of sewer line in the Mount Sequoyah area

$ 1, 400, 000 estimated cost; final design under way

Final design under way by Garver Engineers

Tentative bid date of September 2008; estimated completion of May 2009

25. 36 ” water line improvements (not shown on map )

Install pressure sustaining valves to maintain positive pressure in water transmission mains; install remote valve activators to isolate sections of the water transmission mains in case of line failure; $ 1, 185, 000 cost

Construction 87. 3 percent complete; estimated completion of July 2008

• Alpha Utilities Inc. contractor

26. Farmington gravity sewer line

Contract 1

Construct 2, 000 ’ of 21 ” gravity line; $ 335, 967 cost

Construction 35. 56 percent complete; estimated completion July 2008

Redford Construction

Contract 2

Construct 12, 322 ’ of 12-24 ” gravity sewer line; $ 2, 800, 000 estimated cost — not yet bid; final design and cost estimate under way by RJN

Tentative bid date of December 2008; estimated completion of November 2009

27. Farmington force main

Construct 10, 500 ’ of 16 ” sewer force main; $ 1, 324, 485 cost

Construction 17. 15 percent complete; estimated completion of February 2009

Garney Construction

28. Farmington lift station

Construct a 3. 0 mgd capacity sewer pump station; $ 1, 697, 881 cost

Construction 1. 62 percent complete; estimaed completion February 2009

JL Bryson Inc., Contractor

29. Farmington sanitary sewer rehab

Unit 1

Construct 3, 655 ’ of 6 ” and 8 ” sewer and 66 point repairs citywide; $ 782, 507 cost

Construction complete

T-G Excavating, contrac tors

Unit 2

Lining of 3, 655 ’ of 6 ” and 8 ” pipe by cured-in-placepipe lining; $ 175, 885 cost

Construction complete

Insituform Inc., contractor

30. Manhold rehabilitation (not shown on map )

Repair approximately 800 manholes using various methods; $ 1, 501, 102

Construction under way; estimated completion February 2009

Kim Construction

32. 2008 SSES (not shown on map )

Evaluate 400 manholes and 175, 000 linear feet of sanitary sewer mains; $ 395, 109 cost

Estimated completion January 2009

RJN Group Inc.

* All completion dates are for substantial completion. Percentage of completion is based on dollars earned as the most recent pay request.