Water sewer improvement projects 1. Hamestring sewer lift station • Construct a 36 million gallon per day (mgd ) capacity sewer pump station; $ 6, 909, 800 cost • Construction substantially complete; estimated completion in May 2008 • Brasfield & Gorrie Contractors 2. 48 ” gravity sewer line — Gregg to Hamestring • Construct 24, 751 ’ of 48 ” gravity sewer pipe line and 3, 876 ’ of 30 ” sewer pressure pipe line; $ 10, 970, 164 cost • Construction substantially complete • Oscar Renda Contractors 3. Force mains — Hamestring to West Plant • Construct 21, 740 ’ of 24 and 30 ” sewer force pipe lines; $ 4, 752, 287 cost • Construction complete • Garney Construction 4. Broyles Road water line • Construct 3, 100 ’ of 12 ” water line; cost included with West Side Water Treatment Plant — No. 5 • Construction complete • Brasfield & Gorrie Contractors Broyles Road • Construct 5, 900 ’ of two-lane asphalt road; $ 3, 737, 966 • Construction 74. 17 percent complete • Estimated completion June 2008 • Dean Crowder Construction 5. West Side Waste Water Treatment Plant • Construct a new 10 mgd (average daily flow ) wastewater treatment plant $ 60, 398, 785 cost • Construction substantially complete • Brasfield & Gorrie Contractors 6. Wetlands mitigation • Construct and plant 25. 5 acres of wetlands • Construction under way in multiple small contracts 7. Owl Creek lift station force main • Upgrade the existing sewer pump station and install 11, 600 ’ of (estimated 15 ” sewer pressure pipe line • Scope of work under review 8. Porter Road to Hamestring sewer line • Construct 14, 100 ’ of 21-24 ” gravity sewer pipe line; $ 7, 186, 957 cost • Construction substantially complete • Oscar Renda Contractors
9. North Street to Poplar to Van Asche Road sewer line
• Construct 13, 900 ’ of mostly 24-33 ” gravity sewer pipe line; $ 4, 433, 820 cost
• Construction complete
• T-G Excavating Contractor
10. Gregg Avenue sewer lift station
• Construct a 19 mgd capacity sewer pump station; $ 1, 527, 000 cost
• Construction substantially complete
• Crossland Heavy Contractors Inc.
11. Old Wire Road to Gregg Avenue sewer line
• Construct 15, 770 ’ of 21-36 ” gravity sewer pipe line; cost included with Porter to Hamestring — No. 8
• Construction substantially complete
• Oscar Renda Contractors
12. East Side Waste Water Treatment Plant renovation
Phase 1 (EP-2 )
• Upgrade odor control, solids handling, headworks at the Noland wastewater treatment plant; $ 14, 836, 631 cost
• Construction complete
• Archer Western Contractors
Phase 1 (EP-4 )
• Upgrade effluent aeration, $ 66, 460 cost
• Construction complete
• BlueinGreen Contractors
Phase 2 (EP-1 )
• Increase wet weather capacity, remove the effluent pumping station; $ 1, 336, 886 cost
• Construction substantially complete
• Wilson Brothers Contractors
Phase 3 (EP-3 )
• Remove effluent pumping station, upgrade aeration basin; $ 1, 646, 900, estimated cost — not yet bid.
• Bid date June 19, 2008; estimated completion of August 2009
13. Mally Wagnon sewer lift station and force main
• Replace sewer pump stations, install 4, 000 ’ of 16 ” sewer force pipe line; $ 1, 393, 880 cost
• Construction substantially complete
• Garney Construction
14. Happy Hollow to Noland Waste Water Treatment Plant sewer line
• Construct 26, 458 ’ of 42 ” gravity sewer pipe line; $ 10, 431, 995 cost
• Construction 81. 70 percent complete; estimated completion date of September 2008
• Rosetta Construction
15. Razorback Road to Happy Hollow sewer line
• Construct 13, 489 ’ of 21-30 ” gravity sewer pipe line; $ 6, 015, 000 estimated cost — not yet bid
• Tentative bid date of August 2008; estimated completion of September 2009
16. South Mountain to Industrial Park sewer line
• Construct 4, 084 ’ of 10 ” gravity sewer pipe line, $ 572, 000 estimated cost — not yet bid • Tentative bid date of August 2008; estimated completion of September 2009 31. Lift station upgrade • Upgrade sewer lift stations 13, 14 and 16; $ 460, 367 cost • Construction 89 percent complete; estimated completion date of July 2008 • OMI is executing work Other major capital
improvements 17. U. S. 62 west water line • Relocating the water line along U. S. 62 due to widening from North Hunter to County Road 647; $ 1, 180, 177 cost • Construction complete 18. Sanitary sewer rehab • Construct 13, 067 ’ of 8-15 ” gravity sewer pipe line at various locations citywide; $ 2, 266, 606 cost • Construction complete • T-G Excavating Contractors 19. North College water line replacement — Maple to North • Replacing old water lines along College Avenue from Maple Street to North Street; $ 1, 377, 141 cost • Construction complete 20. 24 ” water line improvements • Replacing water lines along Custer Lane and Morningside Drive; $ 908, 710 cost
• Construction complete
• Crossland Heavy Contractors
21. Razorback Road water line relocation
• Relocating water line along Razorback Road due to widening from 6 th Street to 15 th street; $ 722, 891 cost
• Construction complete
22. Arkansas 16 water line relocation — Rupple Road to Double Springs Road
• Relocating the water line along Arkansas 16 due to widen Rupple Road to Double Springs Road; $ 1, 591, 426 cost
• Construction complete
23. Mount Sequoyah water and sewer
• Construct approximately 6, 900 ’ of water line and 600 ’ of sewer line in the Mount Sequoyah area
• $ 1, 400, 000 estimated cost; final design under way
• Final design under way by Garver Engineers
• Tentative bid date of September 2008; estimated completion of May 2009
25. 36 ” water line improvements (not shown on map )
• Install pressure sustaining valves to maintain positive pressure in water transmission mains; install remote valve activators to isolate sections of the water transmission mains in case of line failure; $ 1, 185, 000 cost
• Construction 87. 3 percent complete; estimated completion of July 2008
• Alpha Utilities Inc. contractor
26. Farmington gravity sewer line
Contract 1
• Construct 2, 000 ’ of 21 ” gravity line; $ 335, 967 cost
• Construction 35. 56 percent complete; estimated completion July 2008
• Redford Construction
Contract 2
• Construct 12, 322 ’ of 12-24 ” gravity sewer line; $ 2, 800, 000 estimated cost — not yet bid; final design and cost estimate under way by RJN
• Tentative bid date of December 2008; estimated completion of November 2009
27. Farmington force main
• Construct 10, 500 ’ of 16 ” sewer force main; $ 1, 324, 485 cost
• Construction 17. 15 percent complete; estimated completion of February 2009
• Garney Construction
28. Farmington lift station
• Construct a 3. 0 mgd capacity sewer pump station; $ 1, 697, 881 cost
• Construction 1. 62 percent complete; estimaed completion February 2009
• JL Bryson Inc., Contractor
29. Farmington sanitary sewer rehab
Unit 1
• Construct 3, 655 ’ of 6 ” and 8 ” sewer and 66 point repairs citywide; $ 782, 507 cost
• Construction complete
• T-G Excavating, contrac tors
Unit 2
• Lining of 3, 655 ’ of 6 ” and 8 ” pipe by cured-in-placepipe lining; $ 175, 885 cost
• Construction complete
• Insituform Inc., contractor
30. Manhold rehabilitation (not shown on map )
• Repair approximately 800 manholes using various methods; $ 1, 501, 102
• Construction under way; estimated completion February 2009
• Kim Construction
32. 2008 SSES (not shown on map )
• Evaluate 400 manholes and 175, 000 linear feet of sanitary sewer mains; $ 395, 109 cost
• Estimated completion January 2009
• RJN Group Inc.
* All completion dates are for substantial completion. Percentage of completion is based on dollars earned as the most recent pay request.