Fayetteville capital improvements
Posted on Monday, July 7, 2008
Water sewer improvement projects 1. Hamestring sewer lift station • Construct a 36 million gallon per day (mgd ) capacity sewer pump station; $ 6, 909, 800 cost • Construction substantially complete; estimated completion in May 2008 • Brasfield & Gorrie Contractors 2. 48 "gravity sewer line - Gregg to Hamestring • Construct 24, 751'of 48 "gravity sewer pipe line and 3, 876'of 30 "sewer pressure pipe line; $ 10, 970, 164 cost • Construction substantially complete • Oscar Renda Contractors 3. Force mains - Hamestring to West Plant • Construct 21, 740'of 24 and 30 "sewer force pipe lines; $ 4, 752, 287 cost • Construction complete • Garney Construction 4. Broyles Road water line • Construct 3, 100'of 12 "water line; cost included with West Side Water Treatment Plant - No. 5 • Construction complete • Brasfield & Gorrie Contractors Broyles Road • Construct 5, 900'of two-lane asphalt road; $ 3, 737, 966 • Construction 74. 17 percent complete • Estimated completion June 2008 • Dean Crowder Construction 5. West Side Waste Water Treatment Plant • Construct a new 10 mgd (average daily flow ) wastewater treatment plant $ 60, 398, 785 cost • Construction substantially complete • Brasfield & Gorrie Contractors 6. Wetlands mitigation • Construct and plant 25. 5 acres of wetlands • Construction under way in multiple small contracts 7. Owl Creek lift station force main • Upgrade the existing sewer pump station and install 11, 600'of (estimated 15 "sewer pressure pipe line • Scope of work under review 8. Porter Road to Hamestring sewer line • Construct 14, 100'of 21-24 "gravity sewer pipe line; $ 7, 186, 957 cost • Construction substantially complete • Oscar Renda Contractors 9. North Street to Poplar to Van Asche Road sewer line • Construct 13, 900'of mostly 24-33 "gravity sewer pipe line; $ 4, 433, 820 cost • Construction complete • T-G Excavating Contractor 10. Gregg Avenue sewer lift station • Construct a 19 mgd capacity sewer pump station; $ 1, 527, 000 cost • Construction substantially complete • Crossland Heavy Contractors Inc.
11. Old Wire Road to Gregg Avenue sewer line • Construct 15, 770'of 21-36 "gravity sewer pipe line; cost included with Porter to Hamestring - No. 8 • Construction substantially complete • Oscar Renda Contractors 12. East Side Waste Water Treatment Plant renovation Phase 1 (EP-2 )
• Upgrade odor control, solids handling, headworks at the Noland wastewater treatment plant; $ 14, 836, 631 cost • Construction complete • Archer Western Contractors Phase 1 (EP-4 )
• Upgrade effluent aeration, $ 66, 460 cost • Construction complete • BlueinGreen Contractors Phase 2 (EP-1 )
• Increase wet weather capacity, remove the effluent pumping station; $ 1, 336, 886 cost • Construction substantially complete • Wilson Brothers Contractors Phase 3 (EP-3 )
• Remove effluent pumping station, upgrade aeration basin; $ 1, 646, 900, estimated cost - not yet bid.
• Bid date June 19, 2008; estimated completion of August 2009 13. Mally Wagnon sewer lift station and force main • Replace sewer pump stations, install 4, 000'of 16 "sewer force pipe line; $ 1, 393, 880 cost • Construction substantially complete • Garney Construction 14. Happy Hollow to Noland Waste Water Treatment Plant sewer line • Construct 26, 458'of 42 "gravity sewer pipe line; $ 10, 431, 995 cost • Construction 81. 70 percent complete; estimated completion date of September 2008 • Rosetta Construction 15. Razorback Road to Happy Hollow sewer line • Construct 13, 489'of 21-30 "gravity sewer pipe line; $ 6, 015, 000 estimated cost - not yet bid • Tentative bid date of August 2008; estimated completion of September 2009 16. South Mountain to Industrial Park sewer line • Construct 4, 084'of 10 "gravity sewer pipe line, $ 572, 000 estimated cost - not yet bid • Tentative bid date of August 2008; estimated completion of September 2009 31. Lift station upgrade • Upgrade sewer lift stations 13, 14 and 16; $ 460, 367 cost • Construction 89 percent complete; estimated completion date of July 2008 • OMI is executing work Other major capital improvements 17. U. S. 62 west water line • Relocating the water line along U. S. 62 due to widening from North Hunter to County Road 647; $ 1, 180, 177 cost • Construction complete 18. Sanitary sewer rehab • Construct 13, 067'of 8-15 "gravity sewer pipe line at various locations citywide; $ 2, 266, 606 cost • Construction complete • T-G Excavating Contractors 19. North College water line replacement - Maple to North • Replacing old water lines along College Avenue from Maple Street to North Street; $ 1, 377, 141 cost • Construction complete 20. 24 "water line improvements • Replacing water lines along Custer Lane and Morningside Drive; $ 908, 710 cost • Construction complete • Crossland Heavy Contractors 21. Razorback Road water line relocation • Relocating water line along Razorback Road due to widening from 6 th Street to 15 th street; $ 722, 891 cost • Construction complete 22. Arkansas 16 water line relocation - Rupple Road to Double Springs Road • Relocating the water line along Arkansas 16 due to widen Rupple Road to Double Springs Road; $ 1, 591, 426 cost • Construction complete 23. Mount Sequoyah water and sewer • Construct approximately 6, 900'of water line and 600'of sewer line in the Mount Sequoyah area • $ 1, 400, 000 estimated cost; final design under way • Final design under way by Garver Engineers • Tentative bid date of September 2008; estimated completion of May 2009 25. 36 "water line improvements (not shown on map )
• Install pressure sustaining valves to maintain positive pressure in water transmission mains; install remote valve activators to isolate sections of the water transmission mains in case of line failure; $ 1, 185, 000 cost • Construction 87. 3 percent complete; estimated completion of July 2008 • Alpha Utilities Inc. contractor 26. Farmington gravity sewer line Contract 1 • Construct 2, 000'of 21 "gravity line; $ 335, 967 cost • Construction 35. 56 percent complete; estimated completion July 2008 • Redford Construction Contract 2 • Construct 12, 322'of 12-24 "gravity sewer line; $ 2, 800, 000 estimated cost - not yet bid; final design and cost estimate under way by RJN • Tentative bid date of December 2008; estimated completion of November 2009 27. Farmington force main • Construct 10, 500'of 16 "sewer force main; $ 1, 324, 485 cost • Construction 17. 15 percent complete; estimated completion of February 2009 • Garney Construction 28. Farmington lift station • Construct a 3. 0 mgd capacity sewer pump station; $ 1, 697, 881 cost • Construction 1. 62 percent complete; estimaed completion February 2009 • JL Bryson Inc., Contractor 29. Farmington sanitary sewer rehab Unit 1 • Construct 3, 655'of 6 "and 8 "sewer and 66 point repairs citywide; $ 782, 507 cost • Construction complete • T-G Excavating, contrac tors Unit 2 • Lining of 3, 655'of 6 "and 8 "pipe by cured-in-placepipe lining; $ 175, 885 cost • Construction complete • Insituform Inc., contractor 30. Manhold rehabilitation (not shown on map )
• Repair approximately 800 manholes using various methods; $ 1, 501, 102 • Construction under way; estimated completion February 2009 • Kim Construction 32. 2008 SSES (not shown on map )
• Evaluate 400 manholes and 175, 000 linear feet of sanitary sewer mains; $ 395, 109 cost • Estimated completion January 2009 • RJN Group Inc.
* All completion dates are for substantial completion. Percentage of completion is based on dollars earned as the most recent pay request.
FEEDBACK:
Something to say about this topic? Submit a Letter to the Editor online






