Fayetteville capital improvements

Posted on Monday, July 7, 2008

Email this story | Printer-friendly version

nwahomes_promo_300x250.jpg

Water sewer improvement projects 1. Hamestring sewer lift station Construct a 36 million gallon per day (mgd ) capacity sewer pump station; $ 6, 909, 800 cost Construction substantially complete; estimated completion in May 2008 Brasfield & Gorrie Contractors 2. 48 "gravity sewer line - Gregg to Hamestring Construct 24, 751'of 48 "gravity sewer pipe line and 3, 876'of 30 "sewer pressure pipe line; $ 10, 970, 164 cost Construction substantially complete Oscar Renda Contractors 3. Force mains - Hamestring to West Plant Construct 21, 740'of 24 and 30 "sewer force pipe lines; $ 4, 752, 287 cost Construction complete Garney Construction 4. Broyles Road water line Construct 3, 100'of 12 "water line; cost included with West Side Water Treatment Plant - No. 5 Construction complete Brasfield & Gorrie Contractors Broyles Road Construct 5, 900'of two-lane asphalt road; $ 3, 737, 966 Construction 74. 17 percent complete Estimated completion June 2008 Dean Crowder Construction 5. West Side Waste Water Treatment Plant Construct a new 10 mgd (average daily flow ) wastewater treatment plant $ 60, 398, 785 cost Construction substantially complete Brasfield & Gorrie Contractors 6. Wetlands mitigation Construct and plant 25. 5 acres of wetlands Construction under way in multiple small contracts 7. Owl Creek lift station force main Upgrade the existing sewer pump station and install 11, 600'of (estimated 15 "sewer pressure pipe line Scope of work under review 8. Porter Road to Hamestring sewer line Construct 14, 100'of 21-24 "gravity sewer pipe line; $ 7, 186, 957 cost Construction substantially complete Oscar Renda Contractors 9. North Street to Poplar to Van Asche Road sewer line Construct 13, 900'of mostly 24-33 "gravity sewer pipe line; $ 4, 433, 820 cost Construction complete T-G Excavating Contractor 10. Gregg Avenue sewer lift station Construct a 19 mgd capacity sewer pump station; $ 1, 527, 000 cost Construction substantially complete Crossland Heavy Contractors Inc.

11. Old Wire Road to Gregg Avenue sewer line Construct 15, 770'of 21-36 "gravity sewer pipe line; cost included with Porter to Hamestring - No. 8 Construction substantially complete Oscar Renda Contractors 12. East Side Waste Water Treatment Plant renovation Phase 1 (EP-2 )

Upgrade odor control, solids handling, headworks at the Noland wastewater treatment plant; $ 14, 836, 631 cost Construction complete Archer Western Contractors Phase 1 (EP-4 )

Upgrade effluent aeration, $ 66, 460 cost Construction complete BlueinGreen Contractors Phase 2 (EP-1 )

Increase wet weather capacity, remove the effluent pumping station; $ 1, 336, 886 cost Construction substantially complete Wilson Brothers Contractors Phase 3 (EP-3 )

Remove effluent pumping station, upgrade aeration basin; $ 1, 646, 900, estimated cost - not yet bid.

Bid date June 19, 2008; estimated completion of August 2009 13. Mally Wagnon sewer lift station and force main Replace sewer pump stations, install 4, 000'of 16 "sewer force pipe line; $ 1, 393, 880 cost Construction substantially complete Garney Construction 14. Happy Hollow to Noland Waste Water Treatment Plant sewer line Construct 26, 458'of 42 "gravity sewer pipe line; $ 10, 431, 995 cost Construction 81. 70 percent complete; estimated completion date of September 2008 Rosetta Construction 15. Razorback Road to Happy Hollow sewer line Construct 13, 489'of 21-30 "gravity sewer pipe line; $ 6, 015, 000 estimated cost - not yet bid Tentative bid date of August 2008; estimated completion of September 2009 16. South Mountain to Industrial Park sewer line Construct 4, 084'of 10 "gravity sewer pipe line, $ 572, 000 estimated cost - not yet bid Tentative bid date of August 2008; estimated completion of September 2009 31. Lift station upgrade Upgrade sewer lift stations 13, 14 and 16; $ 460, 367 cost Construction 89 percent complete; estimated completion date of July 2008 OMI is executing work Other major capital improvements 17. U. S. 62 west water line Relocating the water line along U. S. 62 due to widening from North Hunter to County Road 647; $ 1, 180, 177 cost Construction complete 18. Sanitary sewer rehab Construct 13, 067'of 8-15 "gravity sewer pipe line at various locations citywide; $ 2, 266, 606 cost Construction complete T-G Excavating Contractors 19. North College water line replacement - Maple to North Replacing old water lines along College Avenue from Maple Street to North Street; $ 1, 377, 141 cost Construction complete 20. 24 "water line improvements Replacing water lines along Custer Lane and Morningside Drive; $ 908, 710 cost • Construction complete Crossland Heavy Contractors 21. Razorback Road water line relocation Relocating water line along Razorback Road due to widening from 6 th Street to 15 th street; $ 722, 891 cost Construction complete 22. Arkansas 16 water line relocation - Rupple Road to Double Springs Road Relocating the water line along Arkansas 16 due to widen Rupple Road to Double Springs Road; $ 1, 591, 426 cost Construction complete 23. Mount Sequoyah water and sewer Construct approximately 6, 900'of water line and 600'of sewer line in the Mount Sequoyah area $ 1, 400, 000 estimated cost; final design under way Final design under way by Garver Engineers Tentative bid date of September 2008; estimated completion of May 2009 25. 36 "water line improvements (not shown on map )

Install pressure sustaining valves to maintain positive pressure in water transmission mains; install remote valve activators to isolate sections of the water transmission mains in case of line failure; $ 1, 185, 000 cost Construction 87. 3 percent complete; estimated completion of July 2008 • Alpha Utilities Inc. contractor 26. Farmington gravity sewer line Contract 1 Construct 2, 000'of 21 "gravity line; $ 335, 967 cost Construction 35. 56 percent complete; estimated completion July 2008 Redford Construction Contract 2 Construct 12, 322'of 12-24 "gravity sewer line; $ 2, 800, 000 estimated cost - not yet bid; final design and cost estimate under way by RJN Tentative bid date of December 2008; estimated completion of November 2009 27. Farmington force main Construct 10, 500'of 16 "sewer force main; $ 1, 324, 485 cost Construction 17. 15 percent complete; estimated completion of February 2009 Garney Construction 28. Farmington lift station Construct a 3. 0 mgd capacity sewer pump station; $ 1, 697, 881 cost Construction 1. 62 percent complete; estimaed completion February 2009 JL Bryson Inc., Contractor 29. Farmington sanitary sewer rehab Unit 1 Construct 3, 655'of 6 "and 8 "sewer and 66 point repairs citywide; $ 782, 507 cost Construction complete T-G Excavating, contrac tors Unit 2 Lining of 3, 655'of 6 "and 8 "pipe by cured-in-placepipe lining; $ 175, 885 cost Construction complete Insituform Inc., contractor 30. Manhold rehabilitation (not shown on map )

Repair approximately 800 manholes using various methods; $ 1, 501, 102 Construction under way; estimated completion February 2009 Kim Construction 32. 2008 SSES (not shown on map )

Evaluate 400 manholes and 175, 000 linear feet of sanitary sewer mains; $ 395, 109 cost Estimated completion January 2009 RJN Group Inc.

* All completion dates are for substantial completion. Percentage of completion is based on dollars earned as the most recent pay request.